Construction Timeline

Construction on the Uptown Market Project began September 19, 2014. Crews with Satterfield Construction removed the old asphalt parking. New storm drainage and the underground water and sewer utilities that will serve the market restrooms were installed. The parking lot was paved and landscaping was installed.

Construction on the remainder of the project began in early April of 2015, with estimated project completion near the end of April 2016. The plans included the market pavilion structure, restroom facilities, interactive fountain, additional landscaping, lighting,  elevated lawn and plaza.

This project was funded with the investment of local hospitality taxes in partnership with the V. Kann Rasmussen Foundation, the Self Regional Healthcare Foundation, the Self Family Foundation, the City of Greenwood, the Greenwood Commissioners of Public Works, and the Greenwood Metropolitan District.

 

March 11th Update: We are very close to project completion. 

lights

December 1st Update: The foundation is being poured for the 3600 square foot interactive fountain.  

 Fountain cement 120115

November 2nd Update: The market pavilion roof trusses are being installed.

roof trusses pavilion 103115

 

September 3rd Update: The market pavilion is going up. Four tall pillars on each end of the structure are being formed.

columns 9 02 15

 

August 17th Update: The work has begun on the market pavilion foundation. This is the smaller of the two end caps of the pavilion.

market foundation 8 17 15

July 23rd Update: The roof  is underway on the restroom facility and the  foundation is underway for pillars of the market pavilion.

roof trusses 72315

 

pillar foundation 72315

June 19th Update: Continuing on schedule despite the extreme heat. 

june 19 construction

May 22nd Update: Foundation of the new restroom facility.

may 22 construction

April 10th Update: Crews have begun removing unsuitable soil from the site.

Phase 1 Construction photos:(The New Parking Lot)